We have light and the ventilation works!
And all the plugs work too including the ones for the safelights.
We've also installed the filter boxes for 2 incoming air vents. One more box needs to be constructed for the incoming heat vent that is in the ceiling on the dry side.

Can't wait until this is finished!

Everything has power now.

And illumination levels are more than adequate.

Here's one of the newly installed filter boxes for the air that is coming in from the furnace. I have to have a little bit of heat in here...

Here's the other side of things. 